258 Rigging

2013 calendar page     full logbook     logbook report

Unknown

Tue 30 Jul 2013    Tue 30 Jul 2013

CaverT/UPrevNext
Becka Mon 29 Jul 2013 Wed 31 Jul 2013
Chris D Sun 28 Jul 2013 Wed 31 Jul 2013
Tue 30 Jul 2013
Becka



Chris finished Holly's rigging off String Theory from yesterday then Becka started the rigging of Procrastination Pot. Chris put in an extra bolt for last drop of String Theory. Continuing the trend of us re-rigging every sodding rope in Tunnocks we re-rigged the bottom rope of String Theory to waste less rope then had to re-rig what I'd done in Procrastination when the rope didn't reach... note to self - sort out decent rigging guides before Expo next year.

Edit this entry.

Survex files on this date:
    caves-1623/107/0730
Wallets on this date:
    2013#26 ropeless sleepless restless ['olly360.bmp', 'olly364.bmp', 'olly366_rot', 'olly358', 'olly361.bmp', 'olly35…
Logbook trips on this date:
    Sleepless
    258 Rigging
    258 Pushing pitch at end of Flap - Determination