204 - 204a - The New Gaffered Rigging Guide

Sun 15 Jul 2007



rigging diagram part 1

rigging diagram part 2

Notes

- Pitches 4-8 can all be strung together with 150-160m rope

- 11mm rope is preferable due to the large amounts of mud

- Take a scrubbing brush to the bottom of Trihang for washing ascenders and wellies

- Tying the bottom of the Cerberus pitch rope to something would be a good idea - it is easy to pull up the end with you!

- Possible QM above Trihang pitch head. Up and behind the pitch head appears to be a tube heading left. Requires bolting up to (although only a couple of metres).